Biiso-Masindi Oil Road Works Disrupt Water Supply to More Than 30 Villages
Construction of the 47-km Biiso–Masindi oil road has disrupted a water pumping system that reportedly served more than 30 villages in the area.
Key Takeaways
Construction of the 47-km Biiso–Masindi oil road has disrupted a water pumping system that reportedly served more than 30 villages in the area.
Residents and local leaders allege that the road alignment was altered during construction, resulting in the destruction of the water system.
The contractor, China Railway Seventh Group Ltd, later acknowledged the loss of the water source and said a borehole had been provided, although residents said it was not functioning.
The Works and Transport Minister has ordered an investigation into the circumstances surrounding the design change and water disruption.
The inspection also raised concerns about road safety, outstanding compensation and the project's seven-year delay.

Why it matters
The incident highlights the importance of coordinating road construction with existing utility infrastructure and community services. A road project can deliver its intended transport function while simultaneously creating a significant service disruption if utility mapping, design changes and mitigation measures are not properly managed.