UGX694bn Wakiso West water project advances towards construction procurement
Uganda's UGX694bn Wakiso West Water Project advances with a UGX47.5bn consultancy contract covering detailed design and preparation for major water infrastructure works.
Key takeaways
The National Water and Sewerage Corporation (NWSC) has signed a UGX47.5 billion consultancy contract for the UGX694 billion Wakiso West Water and Sanitation Project.
The consultancy agreement was signed on 3 November 2026.
The project targets more than one million people across parts of Kampala, Wakiso, Entebbe and Mpigi.
The infrastructure includes a new water treatment plant at Bwerenga, transmission and distribution pipelines, pumping stations and storage reservoirs.
The consultancy assignment will cover detailed engineering design and preparation of construction tender documentation. The main construction contractor has not yet been appointed.
Why it matters
Rapid urban expansion across Greater Kampala has increased pressure on existing water infrastructure, leaving some communities dependent on private water vendors.
The Wakiso West project is intended to expand bulk water production and distribution capacity while improving access to affordable water in underserved urban and peri-urban communities.
Its significance extends beyond the water sector: the scale of the proposed investment creates a substantial future pipeline of civil engineering, mechanical, electrical and specialist infrastructure procurement.

Read more...
Project fact sheet
Item | Details |
Project | Wakiso West Water and Sanitation Project |
Sector | Water supply and sanitation |
Promoter | Ministry of Water and Environment / NWSC |
Project value | UGX694bn (approx. €145m) |
Consultancy contract | UGX47.5bn |
Consultancy consortium | NIRAS and Fichtner, with local subconsultants |
Location | Greater Kampala, Wakiso and Mpigi |
Beneficiaries | Over one million people |
Consultancy phase | 20 months |
Status | Detailed design and tender preparation |
Planned infrastructure components
Component | Planned provision |
Water treatment plant at Bwerenga | 62.5 million litres/day |
Raw water intake capacity | Up to 200 million litres/day |
Transmission mains | 94.2 km |
Secondary mains | 78.5 km |
Pumping stations | 4 |
Storage reservoirs | 5 |
Combined reservoir capacity | Over 15.25 million litres |
Community water dispensers | 941 |
The project also includes a faecal sludge treatment facility at Ssekiwunga with a planned capacity of 400 cubic metres per day, alongside distribution infrastructure targeting underserved communities.
The procurement pipeline
The immediate development is the award of the engineering consultancy, not the commencement of physical construction.
The 20-month assignment is expected to produce detailed engineering designs and tender documentation to guide subsequent construction procurement.
This is an important distinction for contractors and suppliers monitoring the project: the main civil works and equipment packages are still future opportunities, not awarded contracts.
Implications for the construction industry
Civil engineering: Future works will involve large-scale pipeline installation, reservoirs and pumping infrastructure.
Mechanical and electrical engineering: Treatment plant equipment, pumps, control systems and associated installations will be required.
Specialist procurement: Opportunities may arise in valves, pipes, instrumentation, water treatment equipment and electromechanical systems.
Consultancy: The project demonstrates the importance of detailed engineering and procurement preparation before large infrastructure investments reach construction.
Market intelligence: Contractors and suppliers should monitor the publication of the main construction tenders.
Key takeaway: The UGX694bn Wakiso West project is progressing through a critical preparation stage. The immediate opportunity is in engineering and consultancy, with the larger construction procurement pipeline still ahead.