SGR land acquisition advances as government pays UGX373bn in compensation
Uganda has paid UGX373bn in SGR compensation, securing 2,108 acres for the Malaba–Kampala railway while UGX472bn remains outstanding
Government has paid UGX373.07bn to 7,721 project-affected persons for the 272km Malaba–Kampala Standard Gauge Railway, securing 2,108 of the 3,536 acres required. Another 5,225 people are awaiting UGX472.45bn in compensation. Approximately 130km of continuous railway corridor is reportedly available, although full construction remains dependent on financial close.

Implications: Land acquisition remains a major determinant of infrastructure project readiness. Outstanding compensation, boundary disputes and contested ownership can delay site possession, while the outstanding financing arrangements remain a separate hurdle to full construction.
Key takeaway: The SGR is making progress on land acquisition, but securing the corridor and securing construction financing must converge before full-scale implementation can proceed.