Bitumen shortage puts Uganda's road construction programme under pressure
Uganda's bitumen shortage is threatening road construction deadlines, with KCCA projects and major highways affected as contractors struggle to secure asphalt surfacing material.
Uganda's road construction programme is encountering an increasingly important supply-chain constraint: contractors are struggling to secure bitumen at the point when several projects are reaching the asphalt-surfacing stage.
The immediate pressure is visible in Kampala, where KCCA says most of its ongoing road projects are between 68% and 70% complete, but shortages of bitumen and unresolved utility relocations could jeopardise the authority's December 2026 completion target. Several roads have progressed through drainage, earthworks and base preparation but cannot move fully into surfacing without the required material.

The problem is not confined to Kampala. On the 103.8-kilometre Koboko–Yumbe–Moyo Road, the contractor reported in September that a long section had already been primed but could not be tarmacked because of delayed bitumen supplies. The project manager identified supply from Iran as a particular concern, warning that prolonged disruption could affect the July 2027 completion deadline.
What this means for Uganda's road programme
The important point is that bitumen becomes a bottleneck late in the construction sequence. A contractor can make substantial visible progress on drainage, formation, gravel and base layers, yet still be unable to turn that progress into a finished paved road if the final surfacing material is unavailable.
That makes the current situation particularly awkward for projects approaching contractual or political deadlines.
KCCA's projects, for example, are already substantially advanced. The authority reports that major drainage works are complete and asphalt laying has begun on several sections, with contractors targeting December handovers. But the remaining works also include walkways, street lighting and road markings, leaving relatively little room for a prolonged interruption in surfacing.
The Koboko–Yumbe–Moyo project illustrates the same problem on a larger highway. The project had reached about 54% completion in September, with 22 kilometres already tarmacked, but the contractor said the shortage was preventing prepared sections from being surfaced.
There is also evidence that this is not entirely a new phenomenon. Uganda's Auditor General has previously documented road projects delayed by scarcity of K1-70 bitumen and other construction materials, indicating that material availability can become a recurring project-delivery risk rather than a one-off inconvenience.
The wider supply-chain question
The more interesting issue is what the shortage tells us about Uganda's construction supply chain.
Road construction is heavily dependent on imported inputs, and a disruption upstream can propagate through numerous projects simultaneously. If contractors are competing for the same limited supply while several government programmes are moving into the surfacing phase, the constraint is no longer simply a contractor's procurement problem, it becomes an infrastructure programme risk.
The current reporting also points to international supply-chain disruption, due to the Middle East conflict, as part of the problem. But we should be careful about attributing the shortage entirely to the Middle East conflict without stronger evidence. What we can say confidently is that Uganda's dependence on imported bitumen leaves road delivery exposed to external supply disruptions.
And that is perhaps the most important lesson.
Implications
Project schedules: Projects nearing completion have less tolerance for prolonged material shortages.
Contractor performance: A contractor may appear to be progressing slowly when the constraint is actually upstream material availability.
Construction quality: Leaving prepared road sections exposed through the rainy season can damage or undermine sub-base, shoulders and drainage works, potentially compromising work already completed.
Rework and cost: If rain damage occurs, contractors may have to repair or reconstruct affected sections before surfacing can proceed, turning a material shortage into an additional cost and programme problem.
Programme risk: If several projects encounter the same constraint simultaneously, government cannot continue to treat each delay as an isolated project-management problem.
Supply-chain resilience: Uganda's expanding infrastructure programme raises the question of whether strategic construction materials need more deliberate supply planning.
Key takeaway
Uganda can have the financing, contractors and prepared roadbeds in place and still fail to deliver roads on schedule if critical construction inputs cannot reach site. The bitumen shortage is therefore more than a temporary inconvenience: it is a reminder that infrastructure delivery depends on the resilience of the entire construction supply chain.
.png)