New Defence Headquarters Reaches 87% Completion
Construction of the new Ministry of Defence and Veteran Affairs (MoDVA) and Uganda People's Defence Forces (UPDF) headquarters at Mbuya has reached 87% completion, with commissioning expected in December 2026.
Key takeaways
Construction began in August 2024.
The project is being executed by the UPDF Engineering Brigade.
The new complex is intended to consolidate the Defence Ministry and military command functions currently spread across different facilities.
Completion and commissioning are currently targeted for December 2026.
The latest progress update followed a site inspection at Mbuya on 14 September. The development comprises a headquarters complex designed to bring the Ministry of Defence and senior military leadership together under one facility.
The project also includes supporting infrastructure and upgraded facilities intended to provide a consolidated administrative and command environment.

The latest reported completion figure provides a useful project-delivery milestone as the development moves into its final phase.
Why it matters: At 87% completion, the project is approaching the handover stage, making the remaining construction, finishing, installation and commissioning works the key areas to watch over the next three months.